arel

Construction of Construction Area for Vande Water Supply Chlorination Tanks

Date: April 2015

 

SITE CHANIA
SUPERVISING AUTHORITY
COST ESTIMATE ₯ 15,000,000
CONTRACTING MARINA MYLONAKI
MANAGEMENT/EXECUTION GEORGIOS KAPSANAKIS
DATE OF COMMENCEMENT 19.08.1997
DATE OF COMPLETION 21.05.1998
FINAL COST ₯ 19,100,000
PRESENT VALUE (*12.38) ₯ 185,631,804