Water Supply of the Municipality of N. Zichni (Phase B’)

Date: November 2011
SITE N. ZICHNI, SERRES
SUPERVISING AUTHORITY MUNICIPALITY OF N. ZICHNI, SERRES
COST ESTIMATE € 425,532.00
CONTRACTING ARIS K. S.A.
MANAGEMENT/EXECUTION ARIS K. S.A.
DATE OF COMMENCEMENT 16.07.2002
DATE OF COMPLETION
FINAL COST € 298,000.00
PRESENT VALUE (*6.15) € 2,618,208.00